Click on photos for larger view. |
 |
 |
 |
| Overhead
CAD |
Non-Intrusive 6" lid |
Depth &
Drainage CAD |
 |
 |
 |
|
Remove Sod and dig 9" to
service lid. |
 |
 |
 |
|
Easy to disconnect and remove
reel. |
 |
 |
 |
| Tie off
supply line. |
Replace
lid. |
Prepare to
backfill. |
 |
 |
 |
|
Use machine initially then
hand dig to prevent pipe or wire damage. |
 |
 |
 |
|
Make sure there are no leaks
before backfilling. |
 |
 |
 |
|
Cut and tie into existing
lateral with isolation and reducer fittings. |
 |
 |
 |
|
Tie into reel where ever
convenient. Use riser for isolation. |
 |
 |
 |
| Pressure
Test |
Complete |
Changing
Hose |
 |
 |
 |
| Level from
side to side ONLY |
Non-Intrusive 6" lid |
Set grade
before backfilling |